St. Louis Canal Road
Houma, LA 70364
|
Phone
: (985) 873-6720
Fax : (985) 873-6874 |
|
|
Terrebonne Parish
Consolidated Government Capital Project Number:
99-EXT-58 |
|
|
| Project
Name: |
Westside Boulevard - Phase A |
| Project
Type: |
Road |
| Project
Year: |
2003 |
| Consultant's
Name: |
GSE Assciates |
| Status Report: |
Construction |
| Description: |
This project consists extending Westside Blvd. from its current terminus at Marie Drive to St. Louis Canal Road. The proposed extension will be approximately 0.45 mi (2,400 ft) long and centered over an existing 66-ft wide pipeline corridor. The typical section consists of four 12-ft concrete travel lanes, 66-ft raised median, 10-ft shoulders and open drainage system. |
|
|
 |