Terrebonne Parish Consolidated Government Capital Project Number:  99-EXT-58
Project Name: Westside Boulevard - Phase A
Project Type: Road
Project Year: 2003
Consultant's Name: GSE Assciates
Status Report: Construction
Description: This project consists extending Westside Blvd. from its current terminus at Marie Drive to St. Louis Canal Road. The proposed extension will be approximately 0.45 mi (2,400 ft) long and centered over an existing 66-ft wide pipeline corridor. The typical section consists of four 12-ft concrete travel lanes, 66-ft raised median, 10-ft shoulders and open drainage system. 